Construction Progress

Turning Vision into Reality at Karo Platinum

The Karo Platinum Project is in a dynamic phase of intensive construction, where years of meticulous planning are transforming into tangible, world-class infrastructure. Significant strides are being made in developing our mining and processing facilities on the Great Dyke.

Execution to date has substantially de-risked the project, with high confidence levels in our reserves, resources, and operational readiness. Throughout this critical phase, we remain dedicated to safety, operational efficiency, and environmental stewardship — ensuring our progress is both rapid and responsible.

Progress at a Glance:

Key Construction Achievements

With significant progress across all construction fronts, the pivotal milestone of first ore in the mill is expected 15 months after financial close. This marks the transition from construction to ore processing and brings the project closer to full operational status.

Processing Plant & Infrastructure – Design and Engineering:

Status: 100% Complete.
Significance: Provides the detailed blueprint for efficient construction, installation, and commissioning of key facilities.

Earthworks:

Status: 100% complete.
Significance:Prepares stable, level ground for the erection of major processing plant structures and supporting facilities.

Civils (Civil Works):

Status: 80% complete.
Significance:Includes foundational concrete structures for the processing plant, administration buildings, and other site infrastructure.

Procurement:

Status: 70% Complete.
Significance: Early procurement reduces risk of delays and supports on-time project delivery.

Fabrication:

Status: 37% complete .
Significance:Represents the manufacturing and assembly of key structural and mechanical components for plant integration.

Bulk Utilities (Water & Power):

Status:Fully secured.
Significance:Ensures reliable resources for ongoing construction and future operational phases.

Looking Ahead:

Key Milestones to Production

With significant progress across all construction fronts, the pivotal milestone of first ore in the mill is expected 15 months after financial close. This marks the transition from construction to ore processing and brings the project closer to full operational status.

Mining Tender awarded:

Status: Tender process commenced.
Significance: Secures a highly capable mining contractor to support operational start-up.

Safety First:

Ensuring Responsible Construction

Karo Mining maintains the highest health and safety standards for all personnel and contractors on site. Robust protocols are in place to ensure a safe working environment, with zero tolerance for unsafe practices.

Environmental responsibility is equally central to our construction approach. Environmental controls and mitigation measures are implemented to minimise our ecological footprint, protecting surrounding communities and the natural environment throughout development.