Construction Progress

Turning Vision into Reality at Karo Platinum

The Karo Platinum Project is in a dynamic phase of intensive construction on the Great Dyke. The project holds a 25-year special mining lease (24 August 2026), with a 2.1 Moz open-pit reserve and an 11.2 Moz resource. Phase 1 is designed for 226 koz of PGMs a year. Tharisa plc holds 78.17% of Karo Mining Holdings as at September 2025.

Execution to date has substantially de-risked the project. Throughout this phase we remain dedicated to safety, operational efficiency, and environmental stewardship.

12 October 2026

Site footage

Drone footage of the Karo Platinum construction site, filmed on 12 October 2026. Sound is on. Press play to watch. The photographs underneath are from the 25 August 2026 site visit. They are not the same day as the film.

25 August 2026

From the site visit

Chirundazi dam wall, 25 August 2026 site visit.

EPSA Internacional laydown area, 25 August 2026 site visit.

Karo Platinum South East haul road, 25 August 2026 site visit.

Mine plan discussion, 25 August 2026 site visit.

Karo Platinum South East pit development, 25 August 2026 site visit.

Metallurgical plant flotation cells, 25 August 2026 site visit.

Progress at a Glance:

Key Construction Achievements

With significant progress across all construction fronts, first ore is expected in H2 2027, as announced by Tharisa plc with the special mining lease on 24 August 2026. Phase 1 is designed for 226 koz a year.

Processing Plant & Infrastructure – Design and Engineering:

Status: 100% Complete.
Significance: Provides the detailed blueprint for efficient construction, installation, and commissioning of key facilities.

Earthworks:

Status: 100% complete.
Significance:Prepares stable, level ground for the erection of major processing plant structures and supporting facilities.

Civils (Civil Works):

Status: 80% complete.
Significance:Includes foundational concrete structures for the processing plant, administration buildings, and other site infrastructure.

Procurement:

Status: 70% Complete.
Significance: Early procurement reduces risk of delays and supports on-time project delivery.

Fabrication:

Status: 37% complete .
Significance:Represents the manufacturing and assembly of key structural and mechanical components for plant integration.

Bulk Utilities (Water & Power):

Status:Fully secured.
Significance:Ensures reliable resources for ongoing construction and future operational phases.

Looking Ahead:

Key Milestones to Production

With significant progress across all construction fronts, first ore is expected in H2 2027, as announced by Tharisa plc with the special mining lease on 24 August 2026. That milestone marks the transition from construction to ore processing.

Mining Tender awarded:

Status: Tender process commenced.
Significance: Secures a highly capable mining contractor to support operational start-up.

Safety First:

Ensuring Responsible Construction

Karo Mining maintains the highest health and safety standards for all personnel and contractors on site. Robust protocols are in place to ensure a safe working environment, with zero tolerance for unsafe practices.

Environmental responsibility is equally central to our construction approach. Environmental controls and mitigation measures are implemented to minimise our ecological footprint, protecting surrounding communities and the natural environment throughout development.